# Finding Significant Project Issues with Machine Learning

**Authors:** Narasimha Rao Vajjhala (American University of Nigeria, Yola, Nigeria) — ORCID 0000-0002-8260-2392; Kenneth David Strang (W3-Research, Data Analytics, St. Thomas, VI, USA) — ORCID 0000-0002-4333-4399
**Type:** Conference paper
**Source:** Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022, Springer Proceedings in Mathematics & Statistics, vol. 401, pp. 13–22, Springer Nature Switzerland
**Published:** 2023-06-07
**DOI:** https://doi.org/10.1007/978-3-031-15175-0_2
**Canonical page:** https://www.narasimharao.net/research/machine-learning-significant-project-issues/
**Indexing:** Scopus · DBLP · Web of Science (CPCI)
**Keywords:** Project; Machine learning; Failure; Random forest; Artificial intelligence; Algorithms; Models; Big data

## Summary

Vajjhala and Strang (2022) applied random forest machine learning to declassified big data on more than 7,000 US military projects to identify the issues most significantly linked with project failure. The model of 94 nodes reached a validation accuracy of 78.4% and a confusion-matrix accuracy of 81% (precision 70.1%, recall 48.8%, specificity 92.6%) with an average ROC area of 85%; the authors recommend logistic regression on the most important factors as the next step.

**Practical implication.** Random forest is a practical first step for finding the factors linked to project failure in large project databases, the authors conclude, to be followed by logistic regression on the most important factors.

- **The Problem:** Only 29% of large-scale software projects are successful according to the Standish Group’s Chaos study, 53% run severely over budget and schedule and 18% deliver no outcomes; the study asks whether machine learning can identify the issues most significantly linked with failure.
- **The Methodology:** Post-positivist analysis of historical big data. After reviewing machine learning typologies, the authors chose random forest over artificial neural networks for numerous mixed-type predictors and a binary outcome (failure, or breach, = 1; success = 0). Records were split into training, validation and test samples, with no more than four predictors per split, and the model was evaluated with out-of-bag accuracy, a confusion matrix and ROC curves.
- **The Core Finding:** Random forest machine learning classified the outcomes of more than 7,000 declassified military projects with 81% accuracy (70.1% precision, 48.8% recall, 92.6% specificity) and an average ROC area of 85%, results the authors judge comparable to similar studies.
- **The Citation:** Vajjhala, N. R., & Strang, K. D. (2022). Finding Significant Project Issues with Machine Learning. In R. Misra, R. Omer, M. Rajarajan, B. Veeravalli, N. Kesswani, & P. Mishra (Eds.), Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022 (pp. 13–22). Springer Nature Switzerland. https://doi.org/10.1007/978-3-031-15175-0_2

## Key findings

- **Finding 1.** The records were split into training (n = 4,500), validation (n = 1,126) and test (n = 1,406) samples, and the random forest grew 94 nodes with no more than four predictors per split.
- **Finding 2.** Validation accuracy was 78.4%; the out-of-bag plot showed 72% accuracy early in training, well below 10 trees, with nearly identical training and testing outcomes.
- **Finding 3.** The confusion matrix gave 958 true negatives, 181 true positives, 190 false negatives and 77 false positives: recall 48.8%, precision 70.1%, specificity 92.6% and accuracy 81%.
- **Finding 4.** The average area under the ROC curve was 85%, and both conditions were predicted accurately up to about an 80% true positive level at a 20% false positive rate.
- **Finding 5.** The project managers in the data averaged 41.9 years of age (SD = 13.3) and 14.1 years of relevant experience (SD = 5.9), and 94% were male, which the authors note skews the model.

Source: Vajjhala & Strang (2022), Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022, Springer Proceedings in Mathematics & Statistics, vol. 401, pp. 13–22, Springer Nature Switzerland. https://doi.org/10.1007/978-3-031-15175-0_2

## The study in detail

**Question.** Could random forest machine learning identify the most significant issues linked with project failure, using declassified big data from the military (defence) industry?

**Finding.** Applied to more than 7,000 declassified military projects (training n = 4,500, validation n = 1,126, test n = 1,406), a random forest of 94 nodes reached a validation accuracy of 78.4% and an accuracy of 81% on the confusion matrix (958 true negatives, 181 true positives, 190 false negatives, 77 false positives), with 70.1% precision, 48.8% recall, 92.6% specificity and an average ROC area of 85%.

**Why it matters.** According to the Standish Group’s Chaos study cited in the paper, only 29% of large-scale software projects are successful. The paper shows how to match a machine learning technique to the research design, data types and data size, and recommends logistic regression on the factors with an importance of at least 0.01 as the next step towards a predictive model of project success or failure.

## Methods and data

| Item | Detail |
|---|---|
| Research question | Can random forest identify the most important factors associated with IT project failure from declassified defence-industry big data? |
| Data | More than 7,000 declassified military projects; project managers’ mean age 41.9, 94% male, mean 14.1 years of experience |
| Samples | Training 4,500; validation 1,126; test 1,406 |
| Method | Random forest classification, 94 nodes, at most four predictors per split; out-of-bag, confusion-matrix and ROC evaluation |
| Main result | Accuracy 81%, precision 70.1%, recall 48.8%, specificity 92.6%, average ROC area 85% |
| Next step | Logistic regression on all factors with an importance of at least 0.01 |

### Standards, datasets and methods named in this study

- [Random forests: the originating paper](https://doi.org/10.1023/A:1010933404324) (Method). Random forest is the technique used to classify the declassified project records; this link opens the paper that introduced it. Breiman, L. (2001). Random forests. Machine Learning, 45(1), 5–32. https://doi.org/10.1023/A:1010933404324

## Definitions and key terms

- **Project failure (in this study):** A project that breached its targets, coded 1, against a successful project with no breach, coded 0. (as used in Vajjhala & Strang (2022))
- **Out-of-bag (OOB) accuracy:** A forecast estimate of accuracy based on data unseen during training. (as used in Vajjhala & Strang (2022))
- **Supervised learning:** Learning from labelled samples: explicitly defined inputs correspond to the known outputs of a target variable, which is used for classification or prediction. (as used in Vajjhala & Strang (2022))

## Opening summary

Since 1984, the Standish Group International has maintained the Chaos database, which investigates the factors of software project success and failure. Over 120,000 IT projects from over 1000 firms have been registered in the database [1]. According to the Standish Group’s Chaos study, just 29% of large-scale software projects are successful [2]. The success criteria were that these initiatives generated acceptable results and were delivered on-time and on-budget. 53% of the initiatives were severely beyond budget and schedule, and 18% of them failed to provide any outcomes [2]. Machine learning algorithms have an advantage over statistical and mathematical machine learning algorithms in that they may learn and improve based on generated predictions by calculating the best estimate that closely matches the observed data and any prior information maintained by the learner [3].

## Limitations

- As with any big data study, the limitations are tied to the returned records and their accuracy, the authors note.
- Ninety-four per cent of the project managers were male, which the authors say skews the model, and the recall of 48.8% means that fewer than half of the failed projects were identified.
- The paper reports the model’s accuracy but does not list which project factors the random forest ranked as most important; the authors recommend logistic regression and other structured-learning techniques as next steps.

## Practical implications

- Project management researchers can use random forest to screen big project data for important factors, then fit a logistic regression on all factors with an importance of at least 0.01, as the authors recommend.
- Organisations with large project repositories can classify project outcomes from historical records with useful accuracy (81% in this study), although the model identified fewer than half of the failed projects (recall 48.8%).
- Researchers choosing a technique can follow the paper’s approach of matching the method to the research design, data types and size — here random forest for mixed-type predictors and a known binary outcome.

## When this research may be relevant

This paper may be relevant to researchers and practitioners working on IT project failure and success factors, machine learning for project management analytics, random forest classification of organisational big data, and defence and government project portfolios.

## How to cite

**APA 7:** Vajjhala, N. R., & Strang, K. D. (2022). Finding Significant Project Issues with Machine Learning. In R. Misra, R. Omer, M. Rajarajan, B. Veeravalli, N. Kesswani, & P. Mishra (Eds.), Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022 (pp. 13–22). Springer Nature Switzerland. https://doi.org/10.1007/978-3-031-15175-0_2

**MLA 9:** Vajjhala, Narasimha Rao, and Kenneth David Strang. “Finding Significant Project Issues with Machine Learning.” Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022, edited by Rajiv Misra et al., Springer Nature Switzerland, 2022, pp. 13–22. https://doi.org/10.1007/978-3-031-15175-0_2.

**IEEE:** N. R. Vajjhala and K. D. Strang, “Finding Significant Project Issues with Machine Learning,” in Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022, R. Misra, R. Omer, M. Rajarajan, B. Veeravalli, N. Kesswani, and P. Mishra, Eds. Springer Nature Switzerland, 2022, pp. 13–22, doi: 10.1007/978-3-031-15175-0_2.

```bibtex
@inproceedings{vajjhala2022machine,
  title = {Finding Significant Project Issues with Machine Learning},
  author = {Vajjhala, Narasimha Rao and Strang, Kenneth David},
  booktitle = {Machine Learning and Big Data Analytics: 2nd International Conference on Machine Learning and Big Data Analytics-ICMLBDA, IIT Patna, India, March 2022},
  series = {Springer Proceedings in Mathematics \& Statistics},
  editor = {Misra, Rajiv and Omer, Rana and Rajarajan, Muttukrishnan and Veeravalli, Bharadwaj and Kesswani, Nishtha and Mishra, Priyanka},
  pages = {13--22},
  year = {2022},
  publisher = {Springer Nature Switzerland},
  doi = {10.1007/978-3-031-15175-0_2},
  url = {https://doi.org/10.1007/978-3-031-15175-0_2}
}
```

## Related publications

- Strang & Vajjhala (2025). [Exploring project manager commitment using machine learning on fuzzy big data](https://www.narasimharao.net/research/project-manager-commitment-machine-learning-big-data/). https://doi.org/10.1504/IJPOM.2025.146727. Across 439 successful US government IT projects with 1,230 features, linear regression outperformed random forest and SVM in predicting project manager commitment tenure.
- Strang & Vajjhala (2023). [Mining Project Failure Indicators From Big Data Using Machine Learning Mixed Methods](https://www.narasimharao.net/research/machine-learning-it-project-failure-indicators-big-data/). https://doi.org/10.4018/IJITPM.317221. Random forest analysis of about 17,430 US government IT projects identified seven failure indicators with 81% recall and a ROC area of 0.849.
- Vajjhala & Strang (2024). [An Exploratory Big Data Approach to Understanding Commitment in Projects](https://www.narasimharao.net/research/machine-learning-project-manager-organizational-commitment-big-data/). https://doi.org/10.1007/978-3-031-60227-6_6. Supervised machine learning on 439 successful US government IT projects showed linear regression best predicted project manager commitment tenure (r² = 0.238), with line of business, experience, network collaboration tools and cross-industry team membership as the strongest features — supporting an association between higher commitment and project success.
- Strang & Vajjhala (2022). [How Bias Impacted the Project Manager Decision to Not Terminate a Failing Project](https://www.narasimharao.net/research/project-manager-bias-failing-project-termination-experiment/). https://doi.org/10.4018/IJITPM.304059. A 400% bonus incentive significantly lowered 16 experienced IT project managers’ likelihood of cancelling a failing project (from 3.438 to 2.438 on a 1–5 scale; p = .005, Cohen’s d = 0.826).
- Vajjhala & Strang (2022). [Impact of Individual Decision-Making Factors on Project Failure](https://www.narasimharao.net/research/individual-decision-making-factors-project-failure/). Project managers’ experience, age and gender were unrelated to the decision to cancel a failing project, while certification was strongly related to a better decision only when a personal incentive biased it (rho = 0.769) and education was negatively related to that biased decision (rho = −0.609).