Testing Risk Management Decision Making Competency of Project Managers in a Crisis

Kenneth David StrangiD & Narasimha Rao VajjhalaiD

The Journal of Modern Project Management, 10(1), pp. 52–71 · Published

Scopus (at publication)Open access

The journal prints the DOI 10.19255/JMPM02904 for this article, but that DOI is not registered with a DOI agency and does not currently resolve, so it is not used as an identifier here. Use the publisher page above.

Summary

Strang and Vajjhala (2022) tested 24 experienced US project managers in a repeated-measures controlled quasi-experiment on how cognitive bias and individual factors affect the decision to cancel a failing project in a crisis. A biasing incentive significantly lowered decision quality, and certification and risk competency were the only individual factors significantly related to good decisions (rho = 0.549 to 0.712). Competent, certified project managers made the best decisions under bias, whereas a certified but incompetent project manager failed to cancel. The authors caution against generalizing because the study was exploratory.

Practical implication. For recruiters and employers of project managers, certification alone does not protect against bias in risk decisions, so competency testing, risk management training and ethics training are recommended.

The Problem
Failing projects are often not cancelled in a crisis, and it is unclear how much cognitive bias and individual factors such as certification, competency and experience drive project managers’ risk decisions.
The Methodology
Repeated-measures controlled quasi-experiment with 24 experienced U.S. project managers (competency test, basic decision, biased decision) analysed with Spearman correlation, MANOVA, repeated-measures ANOVA, Friedman test and post-hoc t-tests.
The Core Finding
In a controlled experiment with 24 experienced US project managers, a biasing incentive significantly lowered decision quality, and certification and risk competency were the only individual factors significantly related to good decisions (rho = 0.549 to 0.712). Competent, certified project managers made the best decisions under bias, whereas a certified but incompetent project manager failed to cancel.
The Citation
Strang, K. D., & Vajjhala, N. R. (2022). Testing Risk Management Decision Making Competency of Project Managers in a Crisis. The Journal of Modern Project Management, 10(1), 52–71. https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM02904

The summary, key findings, methods, implications and relevance notes on this page are this website’s own description of the paper, written from the published abstract and text. The official abstract and citation details are given further down.

Key findings

  1. Finding 1. The experiment tested 24 U.S.-based project managers with at least 5 years of experience (mean age 42.5, 71% male, mean experience 11 years, 50% certified) on a simulated failing military software project hit by a COVID-19 risk event.
  2. Finding 2. The 24 project managers averaged 55% (SD = 31%) on the PERT-based risk competency test, and slightly less than half passed with a score of 60% or higher.
  3. Finding 3. Certification (rho = 0.549, p < .01 basic; rho = 0.712, p < .001 biased) and competency (rho = 0.680 and 0.681, p < .001) were significantly correlated with the decision to cancel the failing project, while gender, education and experience were not.
  4. Finding 4. The MANOVA showed that certified versus uncertified project managers differed significantly across both decisions (F = 17.824, Pillai = 0.652, p < .001), as did competent versus not competent project managers (F = 3.723, Pillai = 0.282, p = .043).
  5. Finding 5. Competent project managers scored significantly higher than non-competent ones in the basic decision (M = 4.71 vs 2.63) and in the biased decision with a 400% bonus incentive (M = 3.91 vs 1.81).
  6. Finding 6. Certified project managers outscored uncertified ones in both the basic (M = 4.58 vs 2.76) and biased (M = 3.55 vs 2.17) conditions, but a certified yet incompetent project manager failed to cancel the failing project under bias (M = 1.7).
  7. Finding 7. Project managers who were both competent and certified made the best decisions in both the basic (M = 4.8) and biased (M = 4.2) conditions, and all hypotheses H2a–H2d were supported.

Source: Strang & Vajjhala (2022), The Journal of Modern Project Management, 10(1), pp. 52–71. Publisher’s page

The study in detail

What question does this paper answer?

How much do cognitive bias and other individual factors (age, gender, education, experience, certification and competency) affect a project manager's risk management decision to cancel a failing project during a crisis?

What did the study find, in detail?

In a repeated-measures controlled experiment with 24 experienced U.S.-based project managers, bias (a 400% bonus offered to keep a failing project going) significantly lowered the quality of decisions, while certification and competency were the only individual factors significantly related to good decisions (e.g., certification rho = 0.549 and 0.712; competency rho = 0.680 and 0.681). Competent and certified PMs made the best decisions in both the basic (M = 4.8) and biased (M = 4.2) conditions, whereas a certified but incompetent PM failed to cancel under bias (M = 1.7).

Why does it matter?

The authors argue that bias such as money and ego can override ethical risk management judgment even among certified project managers, which could be a problem for recruiters who rank certification highly without seeking evidence of competency. They suggest certified PMs receive additional risk management training, that certification courses include experiential exercises on quantifying and mitigating risks, and that employers offer short ethics or organizational refresher courses.

Methods and data

Design, data and results of Testing Risk Management Decision Making Competency of Project Managers in a Crisis
Research questionHow much do cognitive bias and other factors impact project manager risk management decision making in a crisis?
DesignRepeated-measures controlled (quasi-)experiment run asynchronously online over one week; every participant received a competency test, a basic (no-incentive) decision and a biased (incentive) decision
Sample24 U.S.-based project managers with at least 5 years of experience, recruited from a LinkedIn group of about 23,000 professional PMs; mean age 42.5, 71% male, mean experience 11 years, 50% certified
MethodsSpearman correlations, Shapiro-Wilk tests, MANOVA, repeated measures ANOVA, Friedman's test and post hoc pairwise t-tests
Main resultBias significantly impacted decisions; only certification and competency were related to good decisions, and competent and certified PMs made the best decisions (M = 4.8 basic, M = 4.2 biased)
ImplicationCertification alone does not protect against bias; competency testing, risk management training and ethics training are recommended
CitationStrang & Vajjhala (2022)

Definitions and key terms

Risk management decision making
The emotional or thinking processes a project manager uses to solve complex problems in a project beyond business-as-usual activities, such as deciding whether to escalate or cancel a failing project after a severe risk event. — as used in Strang & Vajjhala (2022)
Prospect theory
A model of decision making under risk in which choices are made between value prospects or gambles, shaped by loss aversion, reference points and decision weights. — as used in Strang & Vajjhala (2022)
Repeated measures design
An experimental design in which every participant receives all treatments, so individual differences remain the only varying factors. — as used in Strang & Vajjhala (2022)

All key terms across the publications →

Abstract

The objective of the current study was to use a rigorous controlled experiment simulating a project failure to measure how cognitive bias and competency impact a PM’s risk management decision making in a crisis while controlling for other project and firm level variables including lying or faking responses. The MANOVA, repeated measures ANOVA controlled experiment and post-hoc analysis techniques were rigorous because the study took place in approximately the same point in time and each participant received all treatments. The 24 respondents in these repeated measures experiment outperforms most psychology factorial research design, which would require a 4 x 24 = 96 sample size to accommodate 3 treatments and a control group. We found bias significantly impacted PM risk management decision making in a crisis, but certification and competency resulted in the best decisions. Generalizations are cautioned due to the exploratory nature of this study. However, the literature review and methods were articulated well enough to encourage replications and extensions by other researchers.

Abstract as published in The Journal of Modern Project Management.

Keywords: Project management; risk management; project manager; decision making; crisis; project failure; repeated measures ANOVA; experiment; MANOVA

Limitations and open questions

  • Generalizations must be cautioned because this was a controlled experiment with only 24 participants based in the U.S.
  • Certification was self-reported and competency was judged solely by the score on one open-book PERT risk calculation test question.
  • All organization-level factors were controlled, so the experimental context may not be equivalent to real-world conditions, reducing generalizability.
  • The bias condition combined money and implied ego; other bias constructs were not tested.
  • Competency scores were transformed into a binary pass/fail field (60% pass) to allow ANOVA and MANOVA; MANCOVA with continuous covariates is recommended.
  • The study was a quasi-experiment conducted asynchronously online, participants self-selected, and lingering sentiments from the first treatment may have affected the second.

Open questions

  • Do other forms of cognitive bias beyond money and implied ego affect project termination decisions, and do results hold with larger, non-U.S. samples and MANCOVA designs?

Open questions from the evidence overview Project management and project success.

Practical implications

  • Recruiters who rank certification highly should also seek evidence of competency, because the authors argue that bias such as money and ego can override ethical risk management judgment even among certified project managers.
  • Certified project managers should receive additional risk management training, and certification courses should include experiential exercises on quantifying and mitigating risks, the authors suggest.
  • Employers should offer short ethics or organizational refresher courses, as the authors suggest.
  • Researchers should cite the study as experimental evidence rather than a population estimate, because the sample size is small.

Drawn from Strang & Vajjhala (2022), The Journal of Modern Project Management, 10(1), pp. 52–71.

When this research may be relevant

This article may be relevant to researchers studying cognitive bias and prospect theory in project decisions, risk management competency versus certification, decisions to terminate failing projects, crisis decision-making, and experimental designs in project management research. Sample size is small, so it is best cited as experimental evidence rather than a population estimate.

Research topics addressed: project management; risk management; project failure; decision making; cognitive bias; project manager competency; PM certification; controlled experiment; repeated measures ANOVA; MANOVA; prospect theory; COVID-19; PERT estimation; United States

How to cite

APA 7
Strang, K. D., & Vajjhala, N. R. (2022). Testing Risk Management Decision Making Competency of Project Managers in a Crisis. The Journal of Modern Project Management, 10(1), 52–71. https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM02904
MLA 9
Strang, Kenneth David, and Narasimha Rao Vajjhala. “Testing Risk Management Decision Making Competency of Project Managers in a Crisis.” The Journal of Modern Project Management, vol. 10, no. 1, 2022, pp. 52–71. https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM02904.
IEEE
K. D. Strang and N. R. Vajjhala, “Testing Risk Management Decision Making Competency of Project Managers in a Crisis,” The Journal of Modern Project Management, vol. 10, no. 1, pp. 52–71, 2022. [Online]. Available: https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM02904
BibTeX
@article{strang2022projectmanager,
  title = {Testing Risk Management Decision Making Competency of Project Managers in a Crisis},
  author = {Strang, Kenneth David and Vajjhala, Narasimha Rao},
  journal = {The Journal of Modern Project Management},
  volume = {10},
  number = {1},
  pages = {52--71},
  year = {2022},
  url = {https://journalmodernpm.com/manuscript/index.php/jmpm/article/view/JMPM02904}
}
RIS
TY  - JOUR
TI  - Testing Risk Management Decision Making Competency of Project Managers in a Crisis
AU  - Strang, Kenneth David
AU  - Vajjhala, Narasimha Rao
JO  - The Journal of Modern Project Management
PY  - 2022
DA  - 2022
VL  - 10
IS  - 1
SP  - 52
EP  - 71
UR  - https://www.narasimharao.net/research/project-manager-risk-decision-bias-crisis-experiment/
LA  - en
ER  - 
Download citation:BibTeXRISCSL-JSONMarkdown

Related work

The study cites large empirical studies of defense and public procurement projects: Eckerd and Snider analysed 1,073 Department of Defense projects and found no significant correlation between contractor factors such as experience, PM certification, age or gender and cost variance or breach[1]; Borbath and colleagues examined 14,836 contractor projects and none of their hypotheses were supported[2]; and Ghossein and colleagues reported a 50% failure rate across 59,816 European Union public procurement projects, with small effect sizes[3]. A LinkedIn-sampled survey of 625 PMs by Brandon and colleagues found experience factors predicted percent success with r2 = 0.025[4]. The experiment is grounded in prospect theory, in which decisions are framed as choices between value prospects shaped by loss aversion and reference points[5], and in findings that heuristics, herding and prospect biases, with overconfidence as the dominant heuristic, can produce irrational investment choices[6].

  1. [1] Eckerd, A., & Snider, K. (2017). Does the program manager matter? New public management and defense acquisition. American Review of Public Administration, 47(1), 36–57. https://doi.org/10.1177/0275074015596376
  2. [2] Borbath, M., Blessner, P., & Olson, B. (2019). An empirical approach to the evaluation of defence contractor performance. International Journal of Logistics Research and Applications, 22(2), 138–153. https://doi.org/10.1080/13675567.2018.1497148
  3. [3] Ghossein, T., Islam, A. M., & Saliola, F. (2018). Public procurement and the private business sector: Evidence from firm-level data. In K. V. Thai, P. J. Salia, & F. A. Mwakibinga (Eds.), Global public procurement: Theories and practices (pp. 21–55). Springer. https://doi.org/10.1596/1813-9450-8575
  4. [4] Brandon, T. P., Allen, B. M., & Menefee, S. J. (2022). Which Experience Factors Predict Overall Expertise and Percent Success? The Journal of Modern Project Management, 9(3), 20-31. https://journalmodernpm.com/index.php/jmpm/article/download/JMPM02802/8
  5. [5] Kahneman, D., & Tversky, A. (1979). Prospect Theory: An Analysis of Decision under Risk. Econometrica, 47(2), 263-292. https://doi.org/10.2307/1914185
  6. [6] Goyal, P., Gupta, P., & Yadav, V. (2021). Antecedents to heuristics: Decoding the role of herding and prospect theory for Indian millennial investors. Review of Behavioral Finance, 13(6). Advance online publication. https://doi.org/10.1108/RBF-04-2021-0073

From the evidence overview What predicts IT project failure and success? Evidence on project managers, bias and team transparency from machine learning and experiments, which cites only works that appear in the studies’ own reference lists. This is a selection, not the full reference list of Strang & Vajjhala (2022).

Related research

2022
Strang & Vajjhala (2022) · International Journal of Information Technology Project Management · DOI 10.4018/IJITPM.304059

A 400% bonus incentive significantly lowered 16 experienced IT project managers’ likelihood of cancelling a failing project (from 3.438 to 2.438 on a 1–5 scale; p = .005, Cohen’s d = 0.826).

2025
Strang & Vajjhala (2025) · Information · DOI 10.3390/info16110955

Team members’ willingness to disclose their past performance evaluations during procurement significantly improved project success after controlling for budget, end-user community size and certification, roughly doubling the explained variance in project success from 9.6% to 18.8%.

2025
Strang & Vajjhala (2025) · International Journal of Project Organisation and Management · DOI 10.1504/IJPOM.2025.146727

Across 439 successful US government IT projects with 1,230 features, linear regression outperformed random forest and SVM in predicting project manager commitment tenure.

2022
Vajjhala & Strang (2022) · IGI Global · DOI 10.4018/978-1-6684-5279-0

The volume compiles evidence on risk and contingency management across nations and industries — from petroleum and automotive risk models to cybersecurity, healthcare informatics and educational inequality — offering business leaders lessons for future crises.

2024
Vajjhala & Strang (2024) · WorldCIST 2024 (World Conference on Information Systems and Technologies) · DOI 10.1007/978-3-031-60227-6_6

Supervised machine learning on 439 successful US government IT projects showed linear regression best predicted project manager commitment tenure (r² = 0.238), with line of business, experience, network collaboration tools and cross-industry team membership as the strongest features — supporting an association between higher commitment and project success.

All publication summaries → · All selected publications →